|
|
|
ACDA Standard for Ducted Systems |
|
|
|
Installation Features:
- Galvanised metal auxiliary drain tray under the fan coil unit in roof space.
- Two separate condensate drains fitted: One from the fan coil unit drain pan, One from the auxiliary drain tray.
- Colourbond metal pipe duct used to conceal external piping and wiring where practical.
- Ductwork size and layout individually tailored to suit the application.
- Balancing dampers fitted as necessary.
- All work carried out by qualified tradesmen.
- Installation and associated ductwork and materials guaranteed against all defects for a period of twelve (12) months.
- All rubbish removed from the site during installation.
Fan Coils
- To be suspended by straps on all 4 corners or placed on plinth as required.
- Fan coil unit to be suspended above the ceiling permitting fall to the drain spigot end.
- Supply air and return air plenums are to be secured properly to the fan coil unit.
- Never obstruct service panel with piping and electrical conduits.
- When positioning fan coils in roof do not cut main support timbers without bracing first. If in doubt seek the relevant professional advice.
Drains/Drip Tray
- Auxiliary drip tray to suit the relevant brand of fan coil unit.
- Drain from auxiliary drip tray to run separately from the main drain of the fan coil unit.
- Both drain lines to be saddled/secured to minimise accidental movement.
Ductwork
- All flexible ducts to be double taped - inner sleeve first, then insulation and outer sleeve. Make sure sheetmetal on fittings is not left exposed.
- If joining fittings together without ducting - joints to be screwed and taped.
- If a full length of duct is not needed do not use - shortest distance is best (except last length to the outlet).
- Don't have sharp bends on ducting.
- Return air ducting to be at least one full length (3 metres) for twin or (6 metres for single) where practical.
- Ducting to be suspended if required.
Zones
- If fitting directly to 'BTO' or 'Y' or 'plenum', make sure zone 'shape' still allows correct operation.
- Install zone so as motor is in a serviceable position.
- Never position a zone directly onto gyprock.
- Zone motors to be fitted to assemblies to meet manufacturers requirements.
Pipework
- All pipework joints to be silver brazed or flare connected as applicable.
- All flares to be correct - pipe reamed and cleaned before flaring.
- Pipe joins to be either swaged or coupled solder joints.
- Pipe insulation joints to be taped.
- Liquid line to follow same route as suction line.
- Insulate pipe right up to unit - do not expose suction/liquid line - especially in ceiling.
- Where possible piping in ceiling to be protected or positioned to prevent accidental usage as a support - so no one 'treads' on it.
- Never leave pipework open for long periods of time - if roughing-in a system make sure pipework is capped off or taped off prior to leaving site.
Electrical
- All wiring to be as required to conform to current S.A.A wiring codes.
- Colour coding of control wiring to be as consistent as possible from job to job.
- All unit connections to be bushed or terminated using knockouts provided.
- Any wiring joints to be 'J Boxed" if required.
- Wiring between indoor and outdoor units, to run with pipework, where possible.
- Before fitting controls, confirm location with customer.
- If lights not earthed, inform customer this needs to be done.
Condenser
- Always position condenser on a level concrete slab/s or plinth or brackets - check with customer that this is the position agreed to.
- Fit vibration rubber under condenser feet.
- Always allow enough space to access condenser service panel.
- Never obstruct service panel with piping and electrical conduits.
- Keep pipe and electrical connections from service ducts to condenser at a minimum length.
|
|